Section Bijeljina - Brcko
23.04.2018
The Bijeljina – Brčko highway section is part of the strategic project of the Republika Srpska, which is the construction of a highway from Belgrade to Banja Luka, through the territory of the Republika Srpska.
- The works are being carried out under the contract on financing, design and execution of works No. 013-1640/23 dated 23.02.2023.
- Total contract value: 346,995,317.94 KM (excluding VAT)
- Design and execution: 274,668,800.00 KM (excluding VAT)
- Financing: 72,326,517.94 KM (excluding VAT)
- Contractor: Group of contractors: "China Overseas Engineering Group Co", Ltd. Building 7, No. 1 Zizhuyuan Road, Haidian District, Beijing, China (authorized representative of the group) and “China Tiesiju Civil Engineering Group Co”, Ltd.; No. 96 Wangjiang East Street, Baohe District, Hefei, Anhui, China (member of the group)
- Financing institutions: “China Construction Bank Corporation Beijing Branch” and “Export-Import Bank of China”.
- The length of the section is about 17 km.
- The deadline for the execution of the works is 1095 days from the start date.
- The deadline for the design is 180 days from the start date.
Description of activities for the implementation of the contract for the design and construction of the Brcko-Bijeljina highway section in April:
- The location conditions for the preparatory works were issued on 25.05.2026.
- The development of the Preliminary Design for the main route is in progress.